P.R. No. 23-0003: Mainline Replacement Program (LGU Funded) Phase II

  • Description: Mainline Replacement Program (LGU Funded) Phase II 
  • Mode of Procurement:  Public Bidding
  • Construction Duration: 408 Calendar days
  • Approved   Budget Cost: P 58,689,757.30
  • Cost of Bid Document: P 50,000.00
  • Date of Pre-Bid: September 21, 2022 @ 2:00PM at the Board Room, 2nd flr, ZCWD Bldg., Pilar Street, Zamboanga City
  • Date of Bid Opening: October 3, 2022 @ 2:00PM at the Board Room, 2nd flr, ZCWD Bldg., Pilar Street, Zamboanga City
  • Omnibus Sworn Statement – b. Omnibus-Sworn-StatementRevised-as-of-07.03.2023

 

 

 

Payment for the applicable fee for the Bidding Documents may be deposited in our ZCWD BID DOCUMENTS PAYMENT ACCOUNT:

Bank:  LANDBANK OF THE PHILIPPINES (LBP)

Account Name:  ZAMBOANGA CITY WATER DISTRICT

Account Number:  0191-3826-84

Account Type: SAVINGS

Bank Branch: LBP Main Branch, LANDBANK Building F. Marcos cor. Valderosa Sts., Pettit Barracks, Zamboanga City

Thereafter, send a screenshot or scanned copy of the DEPOSIT/CONFIRMATION SLIP to our email address, bac@zcwd.gov.ph, on or before the deadline for the submission of bids.

 

Please refer to the link below for the scheduled Zoom Meeting (Pre-Bid Conference):

Pre-Bid Conference for Mainline Replacement Program II under PR No. 23-0003
Thursday, September 21 · 2:00 – 6:00pm
Time zone: Asia/Manila

Google Meet joining info
Video call link: https://meet.google.com/xvg-fphz-pja

 

Please refer to the link below for the scheduled Zoom Meeting (Bid Opening):

Public Bid Opening for Mainline Replacement Program II under PR No. 23-0003
Tuesday, October 3 · 2:00 – 6:00pm
Time zone: Asia/Manila

Google Meet joining info
Video call link: https://meet.google.com/sak-qkgf-vac